The hazard being tested
An island forms when the utility disconnects but a distributed source keeps supplying local load. The line stays live, which endangers anyone working on it and risks out-of-phase reclosure damaging equipment when the utility returns. Grid-tied inverters must therefore detect the island and stop supplying within a defined time.
Why a resonant load is required
Inverters detect islanding from voltage and frequency excursions. If the local load does not match the inverter output, an obvious excursion appears the instant the grid opens and the inverter trips immediately — the easiest case to pass, and not representative of the real hazard. The standards therefore require an RLC circuit tuned so that both active and reactive power match the inverter output, giving a resonant condition with quality factor Qf around 1, where voltage and frequency stay as steady as possible after disconnection and the worst-case detection time can be measured.
Common pitfalls
Step resolution too coarse to approach the balance point; reactor inductance departing from its nominal value with current; imprecise timestamping of the disconnect switch; and the inverter's own output drifting with temperature so the balance point moves. A platform with fine steps and an automatic tuning routine cuts the point-by-point search down substantially.
장비에 맞는 구성과 견적이 필요하십니까? 시험 엔지니어가 1영업일 이내에 회신드립니다.
엔지니어와 상담